Saturday, January 28, 2012

Uh-oh...

I think I may have spoken too soon. Work has ground to a halt…



The concrete trucks are coming up the Hume from Kilmore, and at Broadford there’s a VicRoads weighbridge.  I think I’ve only seen this place open once in the past 12 months, and naturally they’ve decided today, of all days, to stop and weigh every truck passing by. We just got the call from the depot to let us know that our next one is stuck in the queue.  He could be there for a while…


They also want to know how much more we need. I’ve got no idea!! The original estimate was 52m3 if all the trenches were 400w with no blow-out or collapse, so I ordered 55m3 to cover us.  They want to know if we need more!


I’ve asked them to send another 3m - the concreters have done some measuring and their guess is we’ll need it. Hope they’re right…

No comments:

Post a Comment