Saturday, September 22, 2012





As promised!



The trenches are all done, and the area below the slab-on-ground has been filled and compacted using the spoil, creating a (mostly) level basis upon which to lay the sandwich panel forms. I wasn’t going to fill this area in, but there was so much soil to deal with from the excavations that I just pushed it down the hill, leveled it off and compacted it.



I’ve booked the trench inspection for Friday arvo, which should give me plenty of time during the day to clean them out and also put in the mini-trench needed for the kitchen drain. Concrete footings are being poured on Saturday at sparrows! :)



(Weather permitting, of course.. The forecast is looking rather ordinary for Friday…)

No comments: